Elkridge, MD
Project consists of the renovation of over 44,200 sf of space including site work and clean room. Scope of work to include, but not be limited to, the following trades. Demolition, site concrete, fencing, asphalt paving, pavement markings & signage, building concrete, structural steel & misc. metal, millwork, solid surface material, roofing, EIFS, caulking, doors/frames/hardware, OH doors, glass & glazing, drywall & acoustics, flooring & base, epoxy flooring, sealed concrete, painting, toilet accessories, lockers, wall & door protection, signage, fire extinguishers, curtain/draperies, window treatments, sprinkler (pre-action, clean room), plumbing (RO system, compressed air/nitrogen piping), HVAC (HEPA), and electric.
RFIs Due: 12 noon, December 11, 2024
Walk-thru: Not available to subs
Deck height will be provided.
Photos are not allowed to be taken on site.
Project requires US Citizens or Resident Alien Green Card status.
Estimated Start Date: TBD
Estimated Completion Date: 07/31/2025
Controls/BMS: See specs & drawings
Fire alarm tie-in: See specs & drawings
Alternate for off hours/weekend work to ensure completion date is met.